The Départemental de Corrèze called on Equans Digital's SIAI (Service Informatique Automatismes Industriels) to undertake major work to secure and optimize the structure.
What are the objectives?
- Secure the continuous power supply to ensure optimum operation of #security equipment in the event of a power cut.
- Modernize the lighting.
- Make the emergency call network reliable.
At 380 meters long, it is the only tunnel in Corrèze that falls under the so-called "Mont-Blanc" regulations due to its length. Completed in 1992, the Cornil tunnel therefore requires special equipment and is subject to regular safety diagnostics.
The tunnel is the only one in Corrèze to fall under the so-called "Mont-Blanc" regulations, due to its length.
A complex, multi-technical renovation requiring :
- GTCInstallation of a centralized technical management system to control the main elements of the structure (energy, lighting, security, etc.) via an automated architecture, cameras, a transmission network and centralized supervision hosted in the IT infrastructure of the Conseil Départemental headquarters in Tulles.
- SIAI SMPThe proposal of our SIAI Smart Multifaceted Platform standard. In combination with the IGNITION supervision software and the GTC, this will make it possible to control various road structures distributed over its territory (tunnel, information panel, video, etc.) at a later date.